How long does it take to build a custom pool in Texas?

How long does it take to build a custom pool in Texas?

A realistic phase-by-phase timeline for building a custom gunite pool in North Texas, from design and permits to excavation, gunite, decking and startup.

By Jesus Arias · 6 min read · Updated October 2026

Short answer: In dry summer weather, most custom gunite pools take about 6 to 8 weeks of construction. Design takes 1 to 2 weeks and permits usually take 1 to 3 weeks before that. Rain is the main cause of delays: after a heavy rain, crews wait 2 to 3 days for the soil to dry before bringing machinery back in.

The phases

PhaseTypical time
Design and contract1–2 weeks
Construction plans, HOA and permits1–3 weeks
Layout and excavation1–2 days
Steel and plumbing rough-in2–4 days
Gunite shellAbout 1 week from ground-break
Utilities, tile, coping and masonry2–3 weeks
Decking and finish work1–2 weeks
Construction total (dry weather)About 6–8 weeks
Interior finish, fill and startupAbout 1 week

Phase by phase

Design and contract

We finalize the 3D design and sign the contract. Your proposal includes our standard selections, and you can upgrade any of them later, with the price difference shown before you decide.

Construction plans, HOA and permits

Construction plans are prepared, the HOA reviews the design if required, and we submit for the city permit. This is the most variable phase and depends on your city and the time of year.

Excavation, steel and plumbing

The pool is laid out and dug, the steel cage is tied, and plumbing for the pool, spa and features is roughed in. The city inspects before gunite.

Gunite

The shell is sprayed and begins curing. Within about a week of breaking ground, you'll see the real shape of your pool.

Utilities, tile, coping and masonry

Electrical, gas and the equipment pad are completed, and waterline tile, coping, raised walls and water features are built.

Decking and outdoor living

The deck goes in, along with patio covers, kitchens and fire features. Larger structures can extend this phase.

Interior finish and startup

The interior finish is applied, the pool is filled, and we start up the equipment and walk you through everything.

What causes delays

  • Rain: the biggest one. Wet clay can't be dug, compacted or driven on safely, so after a heavy rain we wait 2 to 3 days for the soil to dry before bringing machinery back in. Rainy stretches are most common in fall, winter and spring.
  • Patio covers, kitchens and other structures: these add time beyond the pool itself.
  • Permit and HOA timing: varies by city and season.
  • Changes mid-build: decisions made after construction starts can affect the schedule.
  • Upgrade selections: your proposal includes standard selections, such as 6x6 porcelain waterline tile. If you upgrade tile, coping or finishes, you'll see the price difference first, and some upgrades have longer lead times.

Thinking about timing? Read the best time of year to build a pool in North Texas.

Frequently asked questions

How long does a pool take to build in Texas?

In dry weather, most custom gunite pools take about 6 to 8 weeks of construction, after 1 to 2 weeks of design and 1 to 3 weeks for permits. Rain adds time.

What's the longest part of building a pool?

Permitting and HOA review often take the longest before construction. During construction, tile, coping, masonry and decking take the most time.

Can you build a pool in winter in Texas?

Yes. Winters are usually mild enough to keep building, but rain causes more delays than in summer, since crews wait 2 to 3 days for the soil to dry after a heavy rain.

Written by Jesus Arias, founder of Ridge Outdoor Living, a custom pool and outdoor living builder in Dallas–Fort Worth. Figures are typical ranges from our projects and are a guide, not a quote.